Finishing and Refurbishment Work – 5-Story Building

Finalization of finishing touches on a four-story residential building and redesign of interior spaces to ensure modernity, comfort, and sustainability.

Client

Anonymous

Location

Yaoundé - Ngousso

Start date

October 1, 2024

End date

December 30, 2024

Project presentation

The project involved completing the finishing touches and partially reconfiguring the two-bedroom apartments, including:

  • A living room with a terrace
  • A kitchen opening onto a terrace
  • A shared bathroom
  • A master bedroom with bathroom, built-in closet, and terrace
  • A secondary bedroom with closet and terrace

Key project milestones included:

  • A thorough technical inspection
  • Suggestions for improvement
  • The creation of 3D renderings for validation

Challenges encountered:

  • Resolving ventilation and air circulation issues
  • Merging the kitchen and dining room to maximize living space
  • Modernization of sanitary facilities
  • Renovation of bathroom waterproofing
  • Upgrading electrical installations
  •  Coordinated intervention by in-house specialists (plumbing, electricity, decoration, tiling, plastering)

Challenge

We faced several major challenges, such as ventilation issues in the existing building, requiring work on the air circuits; the reconfiguration of spaces to merge the kitchen and dining room in order to optimize volumes; the complete modernization of sanitary facilities and electrical installations; and the total refurbishment of the waterproofing in the bathrooms to ensure the durability of the entire project, mobilizing a multidisciplinary team specializing in each trade.

When it became real